Company:    BAE Systems – Armored Division

Industry:    Defense / Heavy Manufacturing

Project:    Mine Resistant Ambush Protected Vehicles

Size:    500 employees

Location:    Sealy, Texas & Fairfield, Ohio

 

Expertise:    Chain Management, Strategic Sourcing, & Program Management

Assignment:    BAE Systems (“BAE”) performs large-scale crisis manufacturing for the U.S. Military. The company was awarded a $500 million contract to produce a new line of armored vehicles. The project entailed providing the entire cabin armor package for the "Mine Resistant Ambush Protected", or MRAP, wheeled vehicle. The vehicles were needed for deployment in Iraq and Afghanistan to protect our war fighters from the devastation created by the IED bombs being used by the insurgents. The contract called for 1,184 vehicles to be produced and delivered within a period of seven (7) months. Producing an average of 169 vehicles per month was a daunting challenge but when coupled with starting from a vantage point of having built less than 5 prototype units, the challenge seemed overwhelming. Failure to meet the delivery schedule would result in two significant negative outcomes. First, there were severe monetary penalties that were included in the original contract. Second, future contract awards were at stake. If the company delivered on time, the chance to gain more business was good. Fall short of meeting the delivery schedule and the company was virtually guaranteed of not receiving additional contracts. MainStream GS was engaged to provide crisis management for strategic sourcing and supply chain management, as well as program management.

Actions:    MainStream GS’ initial goal was to identify the top 25 - 30 parts and/or suppliers where manufacturing issues could cause delivery delays thus putting BAE in a potential breach of contract scenario. Once the critical parts were identified we established primary and back-up sourcing capabilities, met with each of the suppliers to create a build-out plan, and monitored the activities of the suppliers. In addition, we reported to BAE and the suppliers on a weekly basis regarding the status of the supply chain and assisted with any other supply chain issues that BAE identified as problematic throughout the program.
Our responsibilities included monitoring key suppliers volume production schedules and identifying alternate suppliers for key product requirement where the primary was unlikely to meet production schedules. We acted as liaison between BAE production and procurement departments and selected key suppliers to ensure their material was being delivered in the specified quantity, at the specified time, at the specific production cell, and with the conditions (orientation, packaging, etc.) specified for efficient material handling. We also developed management reporting tools that provided status updates on all critical items as well as implemented feedback and communication systems both internal and external that allowed for critical communications to and from key suppliers. 
We knew that the project would require a distinct forward-looking approach to managing the supply chain. To that end we needed to build planning and communication tools and systems where issues would be identified weeks ahead of when they would cause production delays, so that corrective action plans could be developed and alternative strategies could be implemented. The methodology we used as a baseline for our systems included the following:

While our system identified numerous problems along the way, the design of our forward looking system allowed us to manage the issues before they became a crisis on the production line. Early identification and implementing backup plans eliminated delivery delays and all associated fines and/or penalties.

 

Results:    BAE delivered all 1,184 MRAP vehicles within the contract delivery schedule. Beyond the supply chain management role, throughout the course of our engagement MainStream GS was able to identify over $2.1 million in direct costs savings thus improving the bottom line results. Since the initial contract award, BAE has been awarded supplementary contracts to build more than 1,300 additional vehicles for the U.S. Military.